Dr Kamal Aziz v. Govt of NCT of Delhi and Ors. & Ors.
Case brief
What is this about?
Petitioners challenged a Restrainment Order, sought restoration of electricity connections removed during demolition, and permission to reconstruct boundary walls on their Jaitpur properties. The Court confined the Restrainment Order to fresh construction, refused reconstruction permission, and directed restoration of electricity within five working days.
What did the court decide?
Restrainment Order confined to restraint against fresh/ongoing construction; BSES directed to restore electricity connections CA Nos. 154959468 and 153029775 within five working days; prayer for recon