Ranjeet Kumar (on His Own Behalf and as Spa Holder for Other Petitioners) v. Delhi Development Authority
Case brief
What is this about?
Writ petition challenging a DDA demand letter and related circulars in the Dwarka CSP Housing Scheme 2025 (eAuction), seeking quashing of the demand, restraint on penal interest and completion of pending construction and statutory approvals. The court noted an earlier interim order due to incomplete facilities; the respondent stated flats were now habitable.
What did the court decide?
Payment of demanded amount without interest/penalty if made by 20.02.2026; amounts paid later liable to interest and penalty.