Ak Renewable Infra Private Limited v. Central Electricity Regulatory Commission & Anr.
Case brief
What is this about?
AK Renewable Infra Private Limited; Central Electricity Regulatory Commission (CERC); Central Transmission Utility of India Limited (CTUIL); writ petition not pressed; disposed of; 300 MW connectivity revocation; bank guarantee invocation; connectivity and financial closure timeline extension; 31.12.2026; CERC listing 11.03.2026; Amit Bansal J; Delhi High Court; 10.03.2026.
What did the court decide?
None; writ petition not pressed and disposed of along with the pending application; CERC requested to take up the petitioner's pending petition with interim reliefs on 11.03.2026. ¶21