Hlk Infrastructure Pvt. Ltd. v. Ajay Kumar
Case brief
What is this about?
Contractor's recovery suit for balance construction payments was dismissed by the trial court on tax and extra-work heads. The High Court held the defendant's delayed objections and continued payments proved consent to extra work and liability for taxes, set aside those findings, and decreed Rs.7,02,856/- with 9% per annum interest from suit filing till realisation.
What did the court decide?
Decree for Rs.7,02,856/- with 9% per annum interest from date of suit filing till realisation, plus costs of suit and appeal.