Ramacivil India Construction Pvt. Ltd. v. Delhi Urban Shelter Improvement Board
Case brief
What is this about?
Delhi High Court execution order disposing OMP (ENF.) (COMM.) 51/2020 (with EX.APPL.(OS) 24/2022 and EX.APPL.(OS) 3060/2022); decree-holder Ramacivil India Construction Pvt Ltd; judgment-debtor Delhi Urban Shelter Improvement Board (DUSIB); release of balance deposited award amount against security to satisfaction of Registrar General, Delhi High Court; part payment already released; calculation issues reserved to fresh petition after disposal of O.M.P. (COMM) 452/2020; counsel Avinash Kumar Trivedi and Rishi Kant Singh; decided 12 November 2025 by Justice Jasmeet Singh.
What did the court decide?
Release of the balance deposited amount to the decree-holder (Ramacivil India Construction Pvt Ltd) subject to furnishing security to the satisfaction of the Registrar General, Delhi High Court; liberty to revive/file a fresh petition in respect of calculation issues after disposal of O.M.P. (COMM) 452/2020.