Era Infra Engineering Limited v. M/S Ircon International Ltd. & Anr.
Case brief
What is this about?
Extension of arbitrator's mandate under Section 29A(4) and (5), Arbitration and Conciliation Act 1996; ERA Infra Engineering Limited v. M/S Ircon International Ltd & Anr.; Delhi High Court; O.M.P.(MISC.)(COMM.) 985/2025; mandate expired 5 September 2024; twelve-month extension granted 02.12.2025; lapsed period regularised; proceedings at final-hearing stage; Justice Amit Bansal; petition disposed of.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal for a further period of twelve (12) months, together with regularisation of the period from 5 September 2024 to the date of the order. ¶6