M/S Mbl Infrastructure Ltd. v. M/S Rpg Infratech
Case brief
What is this about?
Petition under Section 29A(5) sought extension of the arbitral tribunal's mandate, which expired on 23.10.2025 while final arguments were underway. Following Rohan Builders, the court regularised the lapsed period and extended the mandate till 30.06.2026.
What did the court decide?
Mandate of Arbitral Tribunal extended till 30.06.2026; period from 23.10.2025 regularised.