Northern Railways v. Shobhit Sharma
Case brief
What is this about?
Delhi High Court order dated 09.10.2025 (Justice Purushaindra Kumar Kaurav) in O.M.P.(MISC.)(COMM.) 834/2025: extension of Arbitrator's mandate for six months with effect from 23.07.2025 granted on petition by Northern Railways with consent of respondent Shobhit Sharma; exemptions application I.A. 25018/2025 allowed and disposed; arbitration; mandate extension; consent-based relief; no statutory sections or case citations; petition disposed of.
What did the court decide?
Mandate of the Arbitrator extended for six months with effect from 23.07.2025; exemptions application I.A. 25018/2025 allowed subject to all just exceptions and disposed of; petition disposed of. ¶¶14