M/S Skb Project (I) Pvt. Ltd. v. Army Welfare Housing Organization
Arbitration and Conciliation Act, 1996 – Section 29A(4) & (5) – Extension of mandate of Arbitral Tribunal by six months – Matter stated to be at the stage of final arguments
Case brief
What is this about?
Delhi High Court, O.M.P.(MISC.)(COMM.) 628/2025, M/S SKB Project (I) Pvt. Ltd. v. Army Welfare Housing Organization, order dated 13.08.2025 by Jasmeet Singh, J. — extension of arbitral mandate under Section 29A(4) & (5) of the Arbitration and Conciliation Act, 1996; six-month extension granted; delay attributed to the arbitration being at the stage of final arguments; unopposed petition (respondent raised no objection); period from 28.07.2025 till the date of order regularised.
What did the court decide?
Extension of the mandate of the Arbitral Tribunal by six months from 13.08.2025, with the period from 28.07.2025 till the date of the order regularised; petition disposed of in those terms. ¶10