M/S Elematic India Pvt. Ltd. v. Vsma Buildcon Pvt. Ltd. & Ors.
Case brief
What is this about?
Petition under Section 29A of the Arbitration and Conciliation Act sought a two-month extension of the arbitral tribunal's mandate. The court found sufficient cause for the delay, extended the mandate by two months, regularised the period from 03.07.2025, and disposed of the petition.
What did the court decide?
Mandate of the Arbitral Tribunal extended by two months from 04.08.2025; period from 03.07.2025 regularised.