Case brief
What is this about?
Consent-based Delhi High Court order (07.07.2025) by Justice Purushaindra Kumar Kaurav in O.M.P.(MISC.)(COMM.) 391/2025: Apex Buildsys Ltd. v. National Automotive Testing and R And D Infrastructure Project — extension by eight months from 08.04.2025 of the time mandate for conclusion of pending arbitration proceedings (claim and counter-claim filed, matter at final stage); exemption application I.A. 15625/2025 allowed subject to all just exceptions; petition disposed of. Useful search terms: arbitration time mandate extension, consent of parties, exemption application, O.M.P.(Misc.)(Comm.).
What did the court decide?
With consent of parties, the prayer in the petition was allowed: the time mandate for conclusion of the pending arbitration proceedings extended for eight months from 08.04.2025; exemption in I.A. 15625/2025 allowed subject to all just exceptions; petition disposed of.