Hiranand Kishinchand Gangwani v. Oyo Apartment Investment LLP
Case brief
What is this about?
Delhi High Court, O.M.P.(MISC.)(COMM.) 253/2025, decided 20.03.2025 by Justice Subramonium Prasad. Keywords: Section 29A(4); Section 29A(5); Arbitration & Conciliation Act 1996; extension of mandate of Arbitrator/Sole Arbitrator; time limit for arbitral award; maintainability of S.29A(4) application after expiry of twelve-month/six-month period; regularization of mandate; Rohan Builders v. Berger Paints 2024 SCC OnLine SC 2494; OYO Apartment Investment LLP; no objection by respondent; award expected by 30.11.2025.
What did the court decide?
Mandate of the Arbitral Tribunal regularized up to 20.03.2025 and extended till 30.11.2025 for pronouncement of the award; petition disposed of along with pending applications, if any. I.A. 7173/2025 (Exemption) also allowed subject to all just exceptions. ¶20