Vogelsang India Private Limited v. Central Organisation for Modernisation of Workshops
Case brief
What is this about?
Petition under Section 29A(4) & (5) of the Arbitration and Conciliation Act, 1996 seeking extension of the arbitral mandate. With no objection from the respondent, the Court regularized the mandate till 03.03.2025 and extended it till 30.10.2025, relying on Rohan Builders.