M/S.Unity-Triveni-Bcpl (Jv) v. Rail Vikas Nigam Ltd.
Case brief
What is this about?
Petition under Section 29A(5) of the Arbitration and Conciliation Act sought extension of the arbitral mandate in a railway construction contract dispute after expiry of the one-year period and a six-month extension. Relying on Rohan Builders v. Berger Paints India Ltd, the Court extended the mandate to 31.12.2025.
What did the court decide?
Mandate of Arbitral Tribunal extended up to 31.12.2025 and the period from 05.01.2025 regularized; petition disposed of with pending applications.