Paramount Wires and Cables Ltd. v. Bharat Sanchar Nigam Limited
Arbitration and Conciliation Act, 1996 – Sections 29A(4) and 29A(5)
Case brief
What is this about?
Delhi High Court (Subramonium Prasad, J.; O.M.P.(MISC.)(COMM.) 1008/2025, decided 12.12.2025): in a cable-supply dispute between Paramount Wires and Cables Ltd. and Bharat Sanchar Nigam Ltd., with final arguments concluded and award reserved but the Arbitral Tribunal's mandate expired on 30.11.2025, the Court regularised the elapsed period and extended the mandate till 31.08.2026 under Sections 29A(4)-(5) A&C Act, relying on Rohan Builders v. Berger Paints (2024 SCC OnLine SC 2494) for post-expiry maintainability; the Court held that challenges to the MSEFC reference and the petitioner's MSME/Small Enterprise status under the MSMED Act, 2006 must be pursued in a Section 16 petition, not in a Section 29A extension petition.
What did the court decide?
Period from 30.11.2025 regularised and mandate of the Arbitral Tribunal extended till 31.08.2026 for pronouncement of the award; petition disposed of along with pending applications, if any.