Surender Rana v. Union of India & Anr.
Case brief
What is this about?
Section 29A(4) Arbitration and Conciliation Act 1996 extension of mandate of Arbitral Tribunal after expiry; Section 29A(5) maintainability of post-expiry application; Section 3G (5) National Highway Act 1956 compensation for acquired land; statutory arbitration by nominated officer GNCT of Delhi Land and Building Department; National Highways Act land acquisition Delhi common Award; Rohan Builders (India) Private Limited v. Berger Paints India Limited 2024 SCC OnLine SC 2494 relied upon; mandate regularized and extended till 20.03.2026; O.M.P. (MISC.) 10/2025 to 14/2025 Delhi High Court; Subramonium Prasad J; no objection by Union of India and NHAI counsel; pleadings completed August 2022; frequent change of statutory arbitrator.
What did the court decide?
Mandate of the Arbitral Tribunal regularized till the date of the order (20.03.2025) and extended for a further period of one year, i.e., till 20.03.2026; petitions disposed of along with pending applications, if any. Exemption applications (I.A. 7182/2025 to I.A. 7186/2025) allowed subject to all just exceptions.