Il and Fs Paradip Refinery Water Limited v. Indian Oil Corporation Limited
Case brief
What is this about?
Arbitration appeal FAO(OS)(COMM) Delhi High Court; BOOT Agreement 29.01.2010 Mahanadi-Cuttack-Paradip water pipeline; MoM 12.02.2015 full and final settlement de-scoped work Cuttack City pipeline; one-time lumpsum Rs.60,39,35,869 acceptance letter 10.11.2015; afterthought claim interest additional financing; political force majeure Clause 15.1.3(iv)/15.3(c) Orissa High Court stay; NTPC Voith and Energy Watchdog distinguished; invocation of force majeure clause; Covid-19 MoF notification 19.02.2020 misplaced; counter-claim best judgment estimate Rs.2 crores set aside patently illegal; scope of S.34/S.37 interference patent illegality Associate Builders MMTC PSA SICAL; Section 37(1)(c) appeal against Section 34 judgment.
What did the court decide?
Appeals partially allowed: the setting aside by the learned Single Judge of the awards on Claim Nos.2 and 3 is sustained, the rejection of Claim No.4 is sustained, and the Arbitral Award on the Respondent's Counter-Claims (Rs.2 crores plus interest) is disallowed/set aside.