M/S Siddhartha Construction Co. v. India Tourism Development Corporation & Anr.
Arbitration and Conciliation Act, 1996 – Sections 12(5), 34, 37 – Seventh Schedule, Entry 1
Case brief
What is this about?
Delhi High Court, FAO(OS) (COMM) 127/2022, decided 02.04.2025 (Prathiba M. Singh & Rajneesh Kumar Gupta, JJ.). M/s Siddhartha Construction Co. v. India Tourism Development Corporation. Keywords: unilateral appointment of arbitrator; Managing Director as appointing authority; Section 12(5); Seventh Schedule Entry 1 (employee of party); waiver by express agreement in writing after dispute; letter acceding to appointment not waiver; Perkins Eastman; Bharat Broadband Network; Govind Singh; Kotak Mahindra Bank; Smaaash Leisure; McLeod Russel (Calcutta HC) not followed here; setting aside arbitral award; Section 34/37 appeals; memorial of Shaheed Bhagat Singh's mother; ITDC. Core holding: arbitrator appointed by ITDC's Managing Director ineligible; award and Section 34 dismissal set aside; appeal allowed.
What did the court decide?
Appeal allowed: the arbitral award dated 9th May, 2020 and the learned Single Judge's order dated 14th September, 2021 are set aside; all pending applications disposed of; parties left free to avail remedies in accordance with law.