P M Projects and Services Private Limited v. Ben and Gaws Private Limited
Arbitration – Substitution of arbitrator – Section 15, Arbitration and Conciliation Act, 1996
Case brief
What is this about?
Substitution of court-appointed arbitrator under Section 15 A&C Act after recusal; no fresh Section 11(6)/Clause 6 invocation needed where initial appointment was by the Court and the party's appointing right stood forfeited. Key terms: Section 15 substitution; Section 11(6) appointment; recusal of sole arbitrator; Section 14 application allegations; fast-track procedure Section 29B; Indemnity Bond Clause 6; Yashwith Constructions applied; M/s Raj Chawla distinguished; Mithlesh Kumar Aggarwal, GMR Ambala Chandigarh Expressways, Tricolor Hotels followed; Ramjee Power Construction and SAP India relied on; mandate extended twelve months; Delhi High Court O.M.P. (T) (COMM.) 71/2025; Purushaindra Kumar Kaurav, J.
What did the court decide?
Petition disposed of: respondent's objections overruled; Ms. Diksha Punia, Advocate substituted as sole Arbitrator on the same terms and conditions as the original arbitrator's appointment vide order dated 04.12.2023; mandate of the arbitrator extended for a further period of twelve months.