Jammu and Kashmir Economic Reconstruction Agency through Its Chief Executive Officer v. Simplex Projects Limited
Case brief
What is this about?
Section 34 A&C Act; patent illegality; liquidated damages vs penalty; genuine pre-estimate of damages; proof of actual loss; Clause 8.7 and 14.15(b) GCC; unilateral adjustment/set-off of LD; counter claim adjudication; loss of car parking charges; loss to public exchequer; government agency delay losses; multi-storied mechanized parking facility Srinagar; JKERA v Simplex Projects; Kailash Nath Associates; Fateh Chand; Maula Bux; BSNL Reliance Communication; ONGC Saw Pipes; Pawan Hans; P.R. Shah; Anglo American Metallurgical Coal; Associate Builders; Dyna Technologies; standard of review of arbitral findings; extension of time; Kashmir Valley unrest delay.
What did the court decide?
This court confined itself to examining whether the rejection of the petitioner's LD claim was vitiated by patent illegality under Section 34; the respondent's Claims 3, 5 and 7, not having been independently challenged under Section 34, were not examined.