Union of India v. Zapdor- Ubc-Abn (Jv )
Case brief
What is this about?
Section 34 Arbitration and Conciliation Act 1996 petition dismissed for non-prosecution; Section 36 enforcement/execution of award dated 06.03.2019; release of balance awarded amount with up-to-date accrued interest to decree holder after 8 weeks; awarded amount deposited in Court, 50% released; Union of India petitioner; ZAPDOR-UBC-ABN (JV) respondent/decree holder; Central Organisation of Railway Electrification (CORE) judgement debtor; Delhi High Court order 02.09.2025; Jasmeet Singh J.
What did the court decide?
Release of the balance awarded amount with up-to-date accrued interest to the decree holder (ZAPDOR-UBC-ABN(JV)) after 8 weeks; separately, the Section 34 petition of Union of India was dismissed for non-prosecution with no relief. ¶¶25