O.M.P. (T) (COMM.) 35/2025, Delhi High Court, decided 22.09.2025 (Jyoti Singh, J.). Substitute Arbitrator appointment under Section 15(2) read with Section 14(1), Arbitration and Conciliation Act 1996; arbitrator withdrawal owing to ill health; revival of arbitration post Settlement Agreement 13.08.2015; respondent evading service, ex parte proceedings of 25.07.2013 unchallenged; Section 12 disclosure; proceedings under DIAC aegis; fees per DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018; continuation from prior stage; merits left open; Techman Shelters Pvt Ltd v. Vijay Chaudhary.
What did the court decide?
Appointment of a Substitute Arbitrator through DIAC; arbitration to be conducted under the aegis of DIAC and its Rules, resuming from the stage left by the erstwhile Arbitrator, subject to Section 12 disclosure; all rights and contentions left open.