Case brief
What is this about?
O.M.P.(COMM) 291/2020, High Court of Delhi, Prateek Jalan, J., decided 08.04.2025 — Section 34 challenge to arbitral award dismissed; scope of judicial review: no reappreciation of arbitrator's evidentiary findings absent perversity; delay in construction contract attributable to employer (UoI) per Hindrance Register (722 days) and correspondence; contractor entitled to escalation/damages for prolongation per K.N. Sathyapalan (2007) 13 SCC 43, T.P. George (2001) 2 SCC 758), Associated Construction (AIR 2008 SC 2911); Clauses 10C and 10CC, GCC CPWD Works 2005; pendente lite and future interest at 9% p.a.; UoI v. Jasbir Singh / M/s Kalsi Engineers; first award of 28.03.2013 previously set aside with consent in O.M.P.(COMM) 846/2013 and remitted.
What did the court decide?
None to the petitioner; the Section 34 petition was dismissed and the arbitral award dated 01.10.2014 — ₹23,09,504/- to the respondent with 9% p.a. simple interest from 10.02.2010 and ₹60,000/- costs — stands undisturbed.