M/S Slr Construction Pvt. Ltd. v. M/S Gail (India) Ltd.
Case brief
What is this about?
Petitioner sought interim arbitration relief against a clause in GAIL's termination order permitting recovery of dues from its other contracts. Respondent's counsel stated it did not presently intend such cross-contract recovery; the court bound the respondent to that statement and left all rights open for arbitral determination.