H.S. Oberoi Buildtech Pvt. Ltd. v. Superior Glass Pvt. Ltd.
Case brief
What is this about?
Delhi High Court; Manoj Jain J.; CM(M) 669/2025; H.S. Oberoi Buildtech v. Superior Glass; recovery suit Rs. 7,32,564/-; adjournment refused 10.03.2025; opportunity to lead evidence closed; one final chance to defendant; DW1 M.S. Oberoi to be examined/cross-examined 17.04.2025 10:00 AM; final arguments same day at Trial Court's convenience; delay cost Rs. 25,000/- imposed on petitioner payable to plaintiff; petition disposed of with pending applications; dasti copy ordered.
What did the court decide?
One final opportunity granted to the defendant to complete its evidence: DW1 Mr. M.S. Oberoi directed to appear before the learned Trial Court on 17.04.2025 at 10.00 AM for examination and cross-examination the same day; Trial Court given liberty to hear final arguments the same day; conditioned on payment of Rs. 25,000/- cost by the petitioner-defendant to the opposite side on 17.04.2025.