Kec Spur Infrastructure Pvt. Ltd. v. Gail (India) Limited
Case brief
What is this about?
Delhi High Court arbitration appointment order, 20.08.2025, ARB.P. 932/2025, Jyoti Singh J. Keywords: Section 11(5) & (6) Arbitration and Conciliation Act 1996; appointment of Sole Arbitrator; KEC Spur Infrastructure Pvt. Ltd. v. GAIL (India) Limited; Sultanpur-Jhajjar-Hissar Pipeline Project Spread-A; Tractebel Engineering PMC; Extended Stay Compensation; Arbitration Clause 54 Special Conditions of Contract; Section 21 notice 10.04.2025; unpaid final bill Rs. 1,83,63,103.51; Justice R.K. Gauba (retd.) appointed arbitrator; Fourth Schedule fee; Section 12 disclosure; merits left open; petition disposed of.
What did the court decide?
Appointment of Mr. Justice R.K. Gauba, former Judge of this Court, as Sole Arbitrator to adjudicate the disputes between the parties; Arbitrator's fee to be fixed as per Fourth Schedule of the 1996 Act; disclosure under Section 12 of the 1996 Act required before entering upon reference; merits expressly left open.