M/S Kapoor Tent and Caterers v. Government of National Territory, Delhi & Anr.
Case brief
What is this about?
Petitioner sought appointment of an arbitrator for non-payment of dues for completed work orders under a GeM arbitration clause. Respondents raised no objection. The Court appointed a Sole Arbitrator, directed a Section 12 declaration and left all rights and contentions open.
What did the court decide?
Petition allowed; dispute referred to Sole Arbitrator Ms. Aditi Sabharwal, Advocate, with directions under Sections 12 and Schedule IV of the Act.