M/S Thermal Engineers and Insulators Pvt. Ltd. v. Govt of NCT of Delhi
Case brief
What is this about?
Section 11(6) Arbitration and Conciliation Act 1996; appointment of sole arbitrator; Section 21 demand notice unanswered; Clause 25 arbitration clause; Contract Agreement dated 31.10.2023; street and side drain improvement works Pratap Garden Uttam Nagar; Govt of NCT of Delhi; DIAC-administered arbitration; DIAC Schedule of Fees; disclosure Section 12(2); sole arbitrator Meha Aggarwal; claim exceeding Rs.85,00,000/-; Delhi High Court ARB.P. 1916/2025; Subramonium Prasad J; 17.11.2025.
What did the court decide?
Petition disposed of with appointment of Ms. Meha Aggarwal as Sole Arbitrator; arbitration to proceed under DIAC aegis with DIAC fee schedule; disclosure under Section 12(2) within two weeks of entering reference; all rights and contentions left open. ¶22