Rajesh Kumar v. M/S Gtl Infrastructure Limited
Case brief
What is this about?
Section 11(5) Arbitration and Conciliation Act 1996; appointment of sole arbitrator; License Agreement dated 06.02.2009; arbitration Clause 21; Supplementary Agreements; prior civil suit for recovery; Section 8 application allowed; invocation notice dated 15.07.2024; no objection by respondent; DIAC; DIAC Rules 2018; Section 12 declaration; arbitrability left open; Chand Chopra; Jasmeet Singh; ARB.P. 1798/2024; decided 18.03.2025.
What did the court decide?
Petition under Section 11(5) allowed; Ms. Chand Chopra, Advocate, appointed Sole Arbitrator; arbitration under DIAC aegis; fees per DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018; Section 12 declaration before entering reference; all rights and contentions left open; parties to approach the arbitrator within two weeks. ¶¶22