M/S Mrk Constructions v. Public Works Department Govt. of NCT of Delhi
Case brief
What is this about?
Keywords: ARB.P. 1596/2025; High Court of Delhi; Amit Bansal J; 04.11.2025; Section 11(6) Arbitration and Conciliation Act 1996; Section 21 notice; Section 12 declaration; appointment of sole arbitrator; limitation/time-barred objection deferred to arbitration; GCC Clause 25; Letter of Acceptance 14.01.2019; arbitrator qualification Graduate Engineer Chief Engineer level; CPWD list / DIAC panel suggestion; DIAC aegis; DIAC Administrative Cost and Arbitrators' Fees Rules 2018; MRK Constructions v Public Works Department GNCTD; Anant Kumar appointed arbitrator; petition disposed of; rights and contentions left open.
What did the court decide?
Appointment of Mr. Anant Kumar as Sole Arbitrator to adjudicate the disputes between the parties; arbitral proceedings to be held under the aegis of the Delhi International Arbitration Centre (DIAC), Delhi High Court; remuneration per the DIAC (Administrative Cost and Arbitrators’ Fees) Rules, 2018; Arbitrator to furnish a declaration under Section 12 of the Act before entering the reference; parties to approach the Arbitrator within two weeks; all pending applications stand disposed of.