Delhi High Court ARB.P. 1478/2025 order 20.11.2025 (Subramonium Prasad J): Section 11(6) Arbitration and Conciliation Act 1996 arbitrator appointment; petitioner M/s K B G Engineers vs Public Works Department Govt of NCT of Delhi; disputed payment Rs.25,10,21,990/- for construction of 232 additional SPS class rooms, Govt schools, PWD Delhi; letters 17.11.2023 and 18.03.2024; Clause 25 GCC; Dispute Resolution Committee not constituted; request of 06.11.2024 unanswered; notice 15.09.2025; Mr. Anant Kumar, Retd. Chief Engineer CPWD appointed Sole Arbitrator; arbitration under DIAC; fees per DIAC Schedule of Fees; disclosure under Section 12(2) of the 1996 Act within two weeks; claims and counter-claims kept open; petition disposed of.
What did the court decide?
Appointment of Mr. Anant Kumar, Retd. Chief Engineer, CPWD, as Sole Arbitrator to adjudicate the payment disputes; arbitration to proceed under DIAC aegis with fees per DIAC Schedule of Fees; disclosure under Section 12(2) of the 1996 Act within two weeks of entering on reference; petition disposed of along with pending application(s).