S.P. Engineering Works Pvt. Ltd. v. Union of India and Anr.
Arbitration and Conciliation Act, 1996 – Section 11 – Appointment of Sole Arbitrator
Case brief
What is this about?
Delhi High Court, ARB.P. 1094/2025, Jasmeet Singh, J. (09.12.2025): Section 11 Arbitration and Conciliation Act 1996 petition allowed with consent of Union of India respondents; Ms. Manisha Singh appointed Sole Arbitrator for disputes under Work Order No. 395-Acs-C-SSB (waterproofing treatment works at railway premises; GCC April 2022, Clause 64; contract value Rs. 1,18,13,042.12/-); arbitration under DIAC aegis; fees per DIAC Rules 2018; Section 12 declaration required; all rights/contentions including arbitrability left open.
What did the court decide?
Petition under Section 11 allowed: Ms. Manisha Singh, Advocate, appointed Sole Arbitrator; arbitration under the aegis and rules of DIAC; remuneration per DIAC (Administrative Cost and Arbitrators' Fees) Rules, 2018; Arbitrator to furnish declaration under Section 12 before entering reference; all rights and contentions (including arbitrability and preliminary objections) left open; parties to approach the Arbitrator within two weeks; petition disposed of in these terms.