Bhilai Engineering Corporation Limited v. Steel Authority of India Limited
Case brief
What is this about?
Bhilai Engineering Corporation Ltd. v. Steel Authority of India Ltd.; W.P.(C) 1934/2025 & CM APPL. 9058/2025 (stay); Delhi High Court; order dated 14.02.2025; Harish Vaidyanathan Shankar, J.; contractor debarment/banning; SCN dated 15.01.2025 seeking nationwide extension of two-year ban imposed 12.09.2024; reply to SCN pending; exclusion from tenders; direction to conclude SCN proceedings within two months; prejudicial decision kept in abeyance for two weeks; petition disposed of with directions; no statute or precedent cited.
What did the court decide?
Direction that the proceedings in respect of the SCN dated 15.01.2025 be concluded within two months, and that any decision taken therein, if prejudicial to the Petitioner, be kept in abeyance for two weeks from communication to the Petitioner; writ petition disposed of accordingly.