Gail India Ltd. v. Pioneer Gas Power Ltd.
Case brief
What is this about?
Petition under Section 29A(4) of the Arbitration and Conciliation Act seeking extension of the sole arbitrator's mandate, which expired on 11.12.2024, in a Gas Transmission Agreement dispute at the cross-examination stage; delay attributed to COVID-19 and the respondent's CIRP. Mandate extended by one year from 11.12.2024.
What did the court decide?
Mandate of Arbitral Tribunal extended for one year from 11.12.2024.