Brij Gopal Construction Co. Pvt. Ltd. v. Delhi Development Authority
Case brief
What is this about?
The Delhi High Court, in an interim application under Section 29A, granted an extension of time for the completion of arbitral proceedings and the making of the arbitral award between the petitioner construction company and the respondent DDA.
What did the court decide?
Extension of time for completion of arbitral proceedings and making of the arbitral award granted till 30.06.2025.