National Highways Authority of India v. Shamlaji Expressway Pvt. Ltd.
Case brief
What is this about?
In an appeal under Section 37 of the Arbitration Act against an interim order, the court permitted NHAI to take over the site to complete the remaining highway work. The court stayed the suspension notice pending the arbitral tribunal's decision on interim relief, requiring parties to constitute the tribunal expeditiously.
What did the court decide?
NHAI permitted to take over site and complete balance works; stay on suspension notice maintained pending arbitral interim orders.