However, it is once again reiterated that the time extension granted by the Respondent to the Claimant on each occasion was subject to its right to impose PRS as per Clause 27 of the GCC (General Conditions of contract), which clearly stipulate that in case the Contractor fails to complete the work within the time period as prescribed under the Contract, the Total Contract Price shall be reduced by ½% of the Total Contract Price per complete work of delay or part thereof subject to maximum of 5% of the Total Contract Price by way of reduction in price for delay and not as penalty. Thus, on account of the above provision, the PRS of Rs.73,55,206/- (Rupees Seventy Three Lac Fifty Five Thousand Two Hundred Six Only) was retained, till last paid bill for the delay in execution of work as a reduction in total Contract price for delay and not as penalty. Further, submissions made in this regard in the afore-mentioned Preliminary Submissions, Preliminary Objections and para wise reply may kindly be read as