enrolled as Municipal Contractor with defendant/MCD. The plaintiff was awarded the work of “Improvement and strengthening of 13.50 m wide road in Sector-22 Rohini in Narela Zone” vide work order No.EE-Project Narela/SYS/2018-19/5 dated 13.04.2018. Pursuant thereto, an Agreement was executed between the parties. The date of start of work was 13.04.2018 and the date of completion was 12.10.2018, in terms of the Agreement. The plaintiff successfully completed the work within time and the bills were submitted to the defendant for payment. The Defect Liability Period/Maintenance Period was five years, which also stands completed on 12.10.2023. The payment against the 2nd RA bill, 3rd RA bill, 4th and Final Bill and 10CA Bill, have been retained by the defendant. It is further submitted that the Liability Period has expired on 12.10.2023 and therefore, the plaintiff is also entitled to the Security amount of Rs.42,12,311/-, which has also been retained in the 4th and final bill.