Rk Wind Limited v. Jeena and Co.
Case brief
What is this about?
The High Court dismissed the petitioner's Section 34 petition challenging an arbitral award. The court upheld the arbitrator's findings that the petitioner caused shipment delays due to unpaid dues to suppliers, rejecting counterclaims and affirming the award of Rs. 1.37 crores plus interest and costs.
What did the court decide?
Petition under Section 34 of the Arbitration Act dismissed; arbitral award affirmed; related applications disposed of.