31. The Respondent wrote letter dated 12.10.2017 to the Claimant whereby it furnished the details of imposition of penalty etc. It is pertinent to mention the Respondent wrongly and in contrary to its own circular imposed interest/penalty. As per the Respondent's representation the Claimant allegedly liable to pay Rs.1,54,60,202/(Rs.1,25,38,602 + Rs.28,21,600) and on the said amount the Respondent levied 2% of TCS i.e. Rs.3,09,204/-. But whereas the Respondent earlier notified the alleged outstanding amount is Rs.1,56,85,234/- (Respondent's letter dated 06.04.2017 may be referred to). Hence, the total amount due and payable is Rs1 ,57,69,406/-. But not Rs.1,56,99,000/- as contended by the Respondent. It is reiterated by that date the Respondent is holding the Claimant's Security Deposit amount of Rs.1,56,99,000/- hence the balance amount if at all payable by the Claimant would be Rs,70,406/-.But as contended above the Respondent wrongly claimed the total outstanding amount payable by the Claimant is Rs.2,17,47,611/-. The Respondent's may be put to strict proof of the same. The Respondent adjusted the security deposit amount of Rs.1,56,99,000/- and claimed the alleged balance amount of Rs.60,48,611 from the Claimant's other toll contract which is situated at Agnampudi Toll Plaza, Visakhapatnam vide letter dated 14.10.2017.”10