Ircon International Ltd. v. Afcons Infrastructure Ltd.
Case brief
What is this about?
Single judge of the Delhi High Court dismissed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an interim award directing the release of performance bank guarantees. The court held that the tribunal's finding on the expiry of the defect liability period was not perverse.
What did the court decide?
Petition under Section 34 of the Arbitration and Conciliation Act, 1996 for setting aside the interim award was dismissed.