M/S Fortune Group v. Chief Engineer PWD (Nh) & Anr.
Case brief
What is this about?
Petitioner, awarded an NH-61 road EPC contract in Nagaland, was terminated and debarred for two years over allegedly fraudulent bank guarantees issued by PNB. The CBI investigation exonerated the petitioner and its officers. The court held the a priori determination required by Clause 4.1 of the RFP was absent and stayed the debarment pending arbitration.
What did the court decide?
Operation of notice of debarment dated 6 July 2023 stayed; respondents restrained from acting on it during arbitral proceedings, subject to further orders therein.