M.V. Omni Projects (India) Ltd. v. Union of India Throgh Dy. Chief Engg., Northern Railway
Case brief
What is this about?
Multiple petitions challenging inconsistent arbitral awards arising from identical railway contracts, where tribunals were constituted under Clause 64 of the General Conditions of Contract, a procedure found legally impermissible by this Court. With counsel's joint agreement, the Court set aside all impugned awards and directed parties to constitute a fresh common arbitral tribunal by mutual conse
What did the court decide?
Impugned arbitral awards set aside; parties at liberty to constitute a fresh tribunal by mutual consent or take legal recourse if difficulty arises.