Nhpc Ltd. v. Apaar Infratech Pvt. Ltd.
Case brief
What is this about?
This judgment sets aside only the interest component of an arbitral award which was contrary to a specific contract condition prohibiting interest, while confirming the validity of the principal award for loss of profit and termination damages.
What did the court decide?
The interest awarded at 10% from the date of reference till the date of award is set aside. The principal award remains valid subject to payment within 10 days to avoid further interest.