Welspun Enterprises Ltd. v. Kasthuri Infra Projects Pvt. Ltd.
Case brief
What is this about?
Single judge held that once an arbitral tribunal is constituted and seized of disputes, the High Court must not pass interim orders under Section 9 unless the situation is emergent. Petition to be decided by the tribunal under Section 17.
What did the court decide?
Disposal of petition with request to arbitral tribunal to decide the arbitration application and the Yes Bank intervention application under Section 17 of the 1996 Act.