The Court dismissed a petition under Section 14(1)(a) of the Arbitration and Conciliation Act, 1996 seeking termination of the arbitrator. It held the petitioner failed to notify the correct fee schedule during the initial appointment and is barred from challenging the mandate now. The arbitrator was found willing to act.
What did the court decide?
Petition under Section 14(1)(a) dismissed; arbitrator's mandate stands.