Union of India v. M/S Ramji Das Dhal Construction Pvt. Ltd.
Case brief
What is this about?
This appeal under the Arbitration and Conciliation Act challenged an interim order granting the release of performance and retention money guarantees. The Court dismissed the petition, holding that the arbitrator's order was sustainable under the contract clauses and that equity principles can be applied by arbitrators.
What did the court decide?
The petition filed under Section 37(2)(b) of the Arbitration and Conciliation Act, 1996, challenging the interim order of the Sole Arbitrator releasing bank guarantees, has been dismissed.