85. Thus, on a fair reading of Clause 9.0.0.0, only the dispute arising out of a NOTIFIED CLAIM of the contractor included in the FINAL BILL in accordance with the provisions of Clause 6.6.3.0 shall be referred to arbitration, that too, subject to Clause 9.0.2.0 and any dispute/matter falling within Clause 9.0.2.0 shall have to be first decided by the General Manager, including, whether or not a claim sought to be referred to arbitration by the contractor is a notified claim. Therefore, if the claim is not a notified claim, as per Clause 6.6.1.0 and the same is not included in the final bill, such a claim is outside the purview of the arbitration agreement. Whether or not a claim sought for arbitration by the contractor is a notified claim or any such matter/dispute is specifically excluded from the scope, purview and ambit of arbitration agreement, such matter/dispute shall have to be first decided by the General Manager prior to the arbitral proceeding with or proceeding further with the reference. Thus, unless there is a decision by the General Manager on whether or not a claim sought to be referred to arbitration by the contractor is a notified claim or not, the arbitrator or Arbitral Tribunal shall have no jurisdiction to entertain such a