M/S.Tempcon Engineers v. Union of India
Case brief
What is this about?
The Delhi High Court disposed of a petition for arbitrator appointment under a CPWD contract. The court directed the respondent to initiate the pre-arbitration mechanism within two months, directing that unresolved additional claims be referred to the existing arbitrator thereafter. The court expressly reserved final adjudication of the claims' merits.
What did the court decide?
Directions for respondent to initiate pre-arbitration mechanism within two months; unresolved additional claims to be lodged with existing arbitrator.