Shipra Infratech Private Limited v. General Electric T &D India Ltd.(Formerly Alstom T&D India Pvt. Ltd.)
Case brief
What is this about?
The court extended the time for the Sole Arbitrator to render the award by four months under Section 29A of the Arbitration and Conciliation Act, 1996, upon consent of parties and finding that proceedings were reserved.
What did the court decide?
Time for arbitrator to render award extended by four months effective February 1, 2020.